How electricity meter installation works

More detail about the process of installing business electricity meters

 Stage
 Description  Responsibility
 1  You will need to arrange with your local distribution company for them to install the cabling into your site.  You
 2  Once they have issued you with an MPAN number please complete our application form.  You
 3  We will then contact you to offer a supply contract for the supply of electricity and also confirm any additional site requirements i.e with Half Hourly metering you must appoint a meter operator to install and maintain the meter on your behalf.  E.ON
 4  You need to return the completed supply contract and any additional paperwork.  E.ON
 5  We will then begin the registration of your supply. (This takes between 4 and 10 working days depending on where your site is based).  E.ON
 6  Once the site is registered we will request a metering date from the meter operator. We will advise you of this date. (The timescales for metering differ from area to area and also dependent on the meter type. We will always look to obtain the best possible meter date for you.  E.ON
 7  Your meter will be installed and energised as long as all siteworks have been completed prior to the meter date.  E.ON
    8  We will then manage your account through to it's first bill.          E.ON